3 Cost Assignment Methods for Project Procurement

3 Cost Assignment Methods for Project Procurements

 

In this article, I want to talk about Cost Assignment Methods for projects.

 

You need to consider the way costs are assigned when establishing the baseline; this is important because the cost should be earned or tracked the same way it is assigned. Here are the methods…

 

#1 50/50 percent rule

50percent credit is given when the activity begins and the remaining 50percent credit is given when the work is completed.

 

For example, if an activity costs $3000, the activity will receive the other $1500 when the work is completed.

 

The basic assumption when using this rule is that activities are approximately the same size. This same method can vary in the percentage values. You can also use 25/75 or 75/25 rule. For instance, some of the variants to the 50/50percent rule include 20/80 and 0/100 rule.

 

Cost Assignment Methods

#2 Percentage complete rule

The completion percentage is estimated and assessed at specified reporting intervals. This is perhaps the most commonly used rule.

 

#3 Weighted milestone

The total work package value is divided up and assigned to milestone intervals within the work package. Each milestone carries a budgeted value. This value is earned when the milestone is achieved. This method works well for long work packages with multiple activities.

 

 

Now your take on this argument.

We would also like to hear what you feel about the topic we discussed today. Your feedback is very important to us. Feel free to drop your comments and recommendations. If you have a contrary opinion, you can drop that too.